The Temporary Terminal C element of the Program involves a reconfiguration of existing Terminal C spaces with the goal of consolidating all of the passenger check-in function south of the existing check-in lobby restrooms. Additionally, the three security checkpoints scattered throughout the facility are being consolidated into the main terminal food court area creating a more efficient process. A secondary benefit of the checkpoint consolidation is that
all of the concessions are to be located post security. Both significant terminal changes are required in order to facilitate the demolition of a portion of the existing terminal facilities to the north of the existing check-in lobby restrooms. This demolition is required to clear the way for the footprint of new modern
Terminal B facility and its two additional gates. Finally, once Terminal B is open for use and all of the airlines currently residing in Terminal C have moved either to Terminal A or B, Terminal C will be fully demolished to make way for future terminal expansion to the South. |
Bid Package #1 - Long Lead Time Items
|
|
Bid Package #1 is comprised of three components that are expected to require significant engineering and/or have lead times that significantly effect the overall construction process. The subsystems are as follows:
1A Ticket Counter Millwork
1B Baggage Handling System
1C Hazardous Material Abatement
Package Release Date >> May 16, 2007
Bids Received >> June 19, 2007
Bid Package #1 Documents >> No Longer Available
Bid Results >> Available For Review
|
Bid Package #2 - Structural Components
|
|
Bid Package #2 is comprised of general construction components needed to complete the basic building structure and to facilitate the installation of finishes. The subsystems are as follows:
2A Manual Baggage Moving
2B Concrete Reinforcing
2C Concrete Material
2D Structural Steel and Misc. Metals
Package Release Date >> June 18, 2007
Bids Received >> Subsystems 2A thru 2C - July 17, 2007, Subsystem 2D - July 24, 2007
Bid Package #2 Documents >> No Longer Available
Bid Results >> Available For Review
|
Bid Package #3 - General Trades
|
|
Bid Package #3 is comprised of finish and relocation components needed to complete the terminal reconfiguration work and to facilitate the tenant relocation process. The subsystems are as follows:
3A EDS Equipment Rigging
3B North Ticket Lobby Demolition
3C Roofing
3D Flashing & Sheet Metal
3E Doors, Frames & Hardware
3F Overhead Coiling Doors
3G Framing and Drywall
3H Acoustical Ceiling
3I Flooring
3J Painting
3K Signage
2L Baggage Scales
Package Release Date >> July 31, 2007
Bids Received >> August 21, 2007
Bid Package #3 Documents >> No Longer Available
Bid Results >> Available For Review
|
Bid Package #4 - Terminal C Demolition 
|
|
Bid Package #4's scope encompasses the work necessary to fully and completely abate and demolish the Terminal C facility once Terminal B is occupied and functioning. The subsystem is as follows:
4.01 Hazardous Material Abatement and Demolition
Package Release Date >> July 15, 2009
Pre-qualification Statement Deadline >> July 31, 2009 at 4:00 PM (PDT)
Deadline for Questions (RFBI) >> July 31, 2009 at 4:00 PM (PST)
Pre-Proposal Conference >> July 27, 2009 at 2:00 PM (PDT)
Bids Due >> August 13, 2009 at 2:00 PM (PDT)
Bid Results >> Available Following Review of Bids
|
Drawings and Specifications
|
|
Please refer to the Drawings and Specs page for information on obtaining drawings and specifications for any of the bid packages. Narratives for all Addenda related to Temporary Terminal C packages will be posted the day of issue at the Terminal C Bid Documents page and drawings will available the same day from the printing vendor.
All inquires related to the Temporary Terminal C bid process should be directed to ttc@sjctaip-opportunities.com.
|