Baggage Handling System

    Home > Elements > BHS


Search:
  

Terminal A Baggage System

A major component of the overall Terminal Area Improvement program is an upgrade to  the current basic baggage handling system in Terminal A and the installation of a brand new system for the Terminal B and North Concourse facility.  Both systems separately include  appropriately 3,000 lf of new conveyor and make-up devices  integrated with inline explosive detection screening equipment.

Baggage Handling Systems Bid Package - Terminals A & B

The scope of work for the Baggage Handling System Bid Package is comprised of two independent turnkey baggage handling systems with inline EDS screening located in Terminal A and B / North Concourse.  Important dates, links to relevant documents and other information pertinent to this bid package are detailed below:

Package Release Date >> June 3, 2008

BHS Pre-qualification Statement >> Must be submitted by June 20, 2008

Pre-Proposal Conference >> June 19, 2008 at 10:00 AM (PST)

Deadline for Questions (RFBI) >> July 15, 2008 at 4:00 PM (PDT)

General Bid Documents >> Available for Downloading

Bid Package Specific  Documents >> No Longer Available

Bid Received >> August 5, 2008 at 2:00 PM (PDT)

Bid Results >> Available For Review

Other Documents

Please refer to the Drawings and Specs page for information on obtaining drawings and specifications for any of the bid packages.  Narratives to all Addenda related to the Baggage Handling System Bid Package will be posted the day of issue at the BHS Bid Documents page and drawings will be available the same day from the printing vendor.

All inquires related to the baggage handling system bid process should be directed to bhs@sjctaip-opportunities.com.